Title: A Test System for Transmission Expansion Planning Studies
This paper introduces a 17-bus 500 kV test system intended for transmission expansion planning (TEP) studies. The overhead lines used in the system are based on an actual 500 kV transmission line geometry. Although several test systems have been developed for various forms of power system analysis, few are specifically tailored for TEP studies at the transmission voltage level, as opposed to the distribution voltage level. Current test systems for TEP studies are limited to single loading conditions only for normal operating conditions, and the majority of these systems are intertwined with issues related to the energy market or devised specifically for integrating new generations and loads into the existing power systems. However, ensuring a test system satisfies both voltage drop and line loading criteria during both normal and all single contingency operations is crucial in TEP studies, and addressing these issues under contingency conditions poses notable challenges. Moreover, practical TEP scenarios involve varied loadings, including peak load and dominant loading (60% of peak load) scenarios, while the existing test systems are configured solely for single loading conditions. To address these technical gaps, this paper introduces the 17-bus test system operating at a transmission voltage level of 500 kV, meeting technical requirements under normal and all single contingency operations for both peak load and dominant load scenarios. Detailed specifications of the proposed test system and load flow analysis at both normal and contingency conditions for different loading conditions are presented. This test system serves as an invaluable resource for TEP studies.  more » « less
Award ID(s):
2306098
PAR ID:
10524674
Author(s) / Creator(s):
;
Publisher / Repository:
MDPI
Date Published:
Journal Name:
Electronics
Volume:
13
Issue:
3
ISSN:
2079-9292
Page Range / eLocation ID:
664
Format(s):
Medium: X
Sponsoring Org:
National Science Foundation
More Like this
  1. This paper presents a 17-bus 500 kV test system for transmission expansion planning (TEP) studies. An actual 500 kV transmission line geometry was used for the overhead lines of this system. Although many test systems have been introduced for different types of power system analysis, those especially for TEP studies at a transmission voltage level, not distribution voltage level, are few. To the best of our knowledge, the introduced test systems for TEP studies, either those combined with electricity market problems or those used to connect a new load or generation to an existing power grid, consider the studies under only normal condition. However, for TEP studies it is needed that a test system meets voltage drop and line loading limits criteria under normal condition as well as all single contingencies, and in this regard, addressing the latter, all single contingencies, is challenging. This paper addresses this technical gap, introducing a 17-bus test system at a transmission voltage level, 500 kV, that meets requirements under normal condition as well as all single contingencies. In addition to presenting all details of this new test system, load flow results under normal condition as well as the worst single contigency are presented. For studies on the TEP, this test system can be an invaluable resource. 
    more » « less
  2. Transmission expansion planning (TEP) is crucial for maintaining the reliable and efficient operation of the power systems, particularly in the face of increasing electricity demand and the integration of renewable energy sources. This paper aims to investigate the application of unconventional high surge impedance loading (HSIL) lines in TEP and presents a comparative analysis of their outcomes against conventional line-based TEP approaches. Starting with a 17-bus 500 kV test system, which can operate well under normal operating condition as well as all single contingency conditions, the objective is to connect a new load located in a new bus, bus #18, to the existing test system via two approaches: using conventional lines and incorporating unconventional HSIL lines. By comparing the number of lines required for the conventional and unconventional approaches, maintaining identical conductor weight per circuit, the effectiveness of unconventional HSIL lines in TEP is evaluated where using only two unconventional HSIL lines is sufficient to connect 1250 MW load demand at bus 18 while three transmission lines are required when using the conventional line. Finally, a thorough economic analysis has been conducted on both TEP scenarios, revealing that implementing unconventional HSIL lines leads to remarkable cost savings and thus can be considered a promising option for TEP studies. 
    more » « less
  3. Transmission expansion planning (TEP) plays a vital role in ensuring the reliable and efficient operation of power systems, especially with the growing demand for electricity and the integration of renewable energy sources. This paper focuses on applying unconventional high surge impedance loading (HSIL) lines in transmission expansion planning and compares their outcomes with conventional line-based transmission expansion planning. Starting with a 17 bus- 500 kV power system connected by a conventional transmission line, the objective is to connect a new load located in a new bus, bus #18, to the existing 17-bus power system via two approaches: using conventional lines and incorporating unconventional HSIL lines. By comparing the number of lines required for the conventional and unconventional approaches, maintaining almost identical conductor volume per circuit, the effectiveness of unconventional HSIL lines in TEP is evaluated where using only two unconventional HSIL lines is sufficient to connect 1000 MW load demand at bus 18 while three lines are required when using the conventional design. 
    more » « less
  4. This paper introduces a new concept in transmission expansion planning based on unconventional lines, termed “smart transmission expansion planning”. Traditionally, the domains of transmission expansion planning (TEP) and transmission line design are separate entities. TEP planners typically rely on the electrical specifications of a limited set of standard conventional line designs to evaluate planning scenarios, ultimately leading to the construction of the selected candidate line. In this context, it is noted that cost-effective scenarios often diverge from meeting the technical criteria of load flow analysis. To address this discrepancy, this paper proposes an alternative approach wherein TEP is conducted based on the specific requirements of the system earmarked for expansion. The transmission expansion planner initiates the process by determining optimal line parameter values that not only meet the operational criteria but also ensure cost-effectiveness. Subsequently, a line is designed to embody these optimal parameters. A detailed comparative analysis is conducted in this study, comparing the outcomes of TEP analyses conducted with conventional lines, unconventional lines, and lines featuring optimal parameters. Through extensive load flow analysis performed under normal and all single-contingency scenarios across three distinct loading conditions (peak load, dominant load representing 60% of peak load, and light load representing 40% of peak load), the results reveal that transmission lines engineered with optimal parameters demonstrate effective operation, with fewer transmission lines required to meet identical demands compared to other approaches. 
    more » « less
  5. In this work, we investigate grid-forming control for power systems containing three-phase and single-phase converters connected to unbalanced distribution and transmission networks, investigate self-balancing between single-phase converters, and propose a novel balancing feedback for grid-forming control that explicitly allows to trade-off unbalances in voltage and power. We develop a quasi-steady-state power network model that allows to analyze the interactions between three-phase and single-phase power converters across transmission, distribution, and standard transformer interconnections. We first investigate conditions under which this general network admits a well-posed kron-reduced quasi-steady-state network model. Our main contribution leverages this reduced-order model to develop analytical conditions for stability of the overall network with grid-forming three-phase and single-phase converters connected through standard transformer interconnections. Specifically, we provide conditions on the network topology under which (i) single-phase converters autonomously self-synchronize to a phase-balanced operating point and (ii) single-phase converters phase-balance through synchronization with three-phase converters. Moreover, we establish that the conditions can be relaxed if a phase-balancing feedback control is used. Finally, case studies combining detailed models of transmission systems (i.e., IEEE 9-bus) and distribution systems (i.e., IEEE 13-bus) are used to illustrate the results for (i) a power system containing a mix of transmission and distribution connected converters and, (ii) a power system solely using distribution-connected converters at the grid edge. 
    more » « less